Projects

RESEARCH PROJECTS

Sl.No Project Title Funded By Project Duration Amount Rs. in lakhs Status
1. Non-Linear Soil-Structure Interaction of Piles on Sloping Ground Department of Science and Technology (DST) 2007-2010 10.16 Completed
2. Evaluation of Geotechnical Properties of Lunar Soil Simulant (LSS) for Chandrayaan- 2 Mission- Lunar Terrain Test Facility ISRO –ISAC, Bangalore Sep 2011-April 2012 3.97 Completed
3. Study on External Dump Slope Stabilization/ Drainage System for Mine – II, NLC NLC, Neyveli Feb 2012-Dec 2012 12.75 Completed
4. Slope stability analysis and design for Mine-1A, NLC NLC, Neyveli June 2012-Dec 2012 6.50 Completed
5. Characterization of Lunar Soil Simulant for Evaluating  Design Criteria of Lunar Structures ISRO - RESPOND Sep 2018-Aug 2021 18.36 Ongoing
6. Soil-Monopile-Wave Interaction study for monopile supported offshore wind turbine SPARC-II, MHRD 48.26 lakh/2019 UK Partner Proposal under review (Proposal-Id : 2652)
7. Geotechnical techniques for the preservation of monuments and historic sites in India SPARC-II, MHRD 47.06 lakh/2019 Italy Partner Proposal under review (Proposal-Id : 2641)

MAJOR CONSULTANCY PROJECTS

Sl. No. Title Sponsoring Agency Status
1 Geotechnical investigations and suitable foundation recommendation for BHEL Expansion Works at Trichy and Thirumayam, Tamilnadu BHEL-Trichy Completed (2009 & 2010)
2 Safe Barrier Design for Open Mining at Mine-II, Neyveli, India NLC, Neyveli Completed (2009)
3 Geotechnical investigations and foundation design for fish landing centers at varies places in the East Coast of Tamilnadu under Tsunami Project Implementation Tsunami Project Implementation Division funded by World Bank Completed (2010)
4 Geotechnical Investigations and foundation recommendation including pile design for  Tamilnadu Slum Clearance Board work in Trichy and Madurai division Tamilnadu Slum Clearance Board Completed (2010 & 2011)
5 Estimation of dynamic soil properties for cooler design for Ultratech Cement Plant at Ariyalur Ultratech Cement Limited Completed (2011)
6 Detailed Geotechnical investigation and foundation recommendation for Yathri Nivas, Srirangam Temple PWD Trichy Completed (2012)
7 Detailed Geotechnical investigation and foundation recommendation for IOCL Mounded Storage at Cochin Bottling IOCL-Cochin Completed (2012)
8 Detailed Geotechnical investigation and foundation recommendation for the proposed new Naval Land at Rameswaram Naval Board Completed (2012)
9 Detailed Geotechnical investigation and foundation recommendation for the proposed new Naval Land at Nagappattinam Naval Board Completed (2012)
10 Detailed Geotechnical investigation and pile foundation analysis for the proposed Railway B.G. line Major Bridge between Nagappattinam and Thiruthuraipoondi Southern Railway Completed (2012)
11 Inspection of pile load test and plate load test for the proposed Railway B.G. line between Nagappattinam and Thiruthuraipoondi Southern Railway Completed(2012 & 13)
12 Detailed Geotechnical investigation and suitable ground improvement recommendation including PVD design for the proposed Railway B.G. line alignment between Nagappattinam and Thiruthuraipoondi Southern Railway Completed (2014)
13 Forensic geotechnical investigation for failed costal diaphragm wall at Nagappattinam fishing harbor Tamilnadu Fisheries Department Completed(2014)
14 Analysis and design of pile foundation for the proposed CPCL oil storage tank at Nagappattinam CPCL Completed(2014)
15 Geotechnical investigations and foundation recommendation for the proposed New IIM Trichy campus IIM Trichy Completed(2014)
16 Geotechnical investigation for the proposed buildings and diaphragm wall at Modasalodai site in Cuddalore district Tamilnadu Fisheries Department Completed(2014)
17 Geotechnical investigation and foundation recommendation for the proposed facilities for submarine rockets RGB-12 & RGB-60 at HAPP Trichy Military Engineering Services/ Garrison Engineering Completed(2014)
18 Geotechnical investigation and foundation recommendation for the proposed new bus stand at Srirangam, Trichy M/s. Jones Lang Lasalle Chennai Completed(2014)
19 Geotechnical investigation and foundation recommendation for the proposed CAMFIL expansion work at Asoor, Trichy CAMFIL Farr Air Filtration India Pvt. Ltd. Asoor, Trichy Completed (2014)
20 Conducting of Sub-soil Investigation at 110KV SS Mayiladuthurai for Construction Staff Quarters for KGTPS Staff Maruthur SE, KGTPS Kuttalam Completed (2014)
21 Detailed Geotechnical investigation and foundation design for the proposed Construction of Dwelling Units at Thimmarayachamuthiram, and Melapandamangalam, Trichy. Tamilnadu Slum Clearance Board, Trichy Completed (2014)
22 Design of Sand drains and performance monitoring of railway embankment between Nagapattinam and Thiruthuraipoondi, Ch. 18000 to 23000 M/s. RR Construction (Railway Contractor) Completed (2014)
23 Design of Prefabricated Vertical Drains and performance monitoring of railway embankment between Nagapattinam and Thiruthuraipoondi, Ch. 13000 to 18000 M/s. Janavi Granites & Builders (Railway Contractor) Completed (2014)
24 Detailed Geotechnical investigation and foundation recommendation for the proposed construction at Ezhimala, Kerala for Indian Naval Academy (Phase-II work) Naval Board / M/s. Mukesh Associates, Salem Completed (2015)
25 Detailed geotechnical investigation and pile foundation analysis and design of the proposed Hi-Tech Gowdon at Nagappatinam project including ground improvement Tamilnadu Civil Supply Corporation (TNCSC) Completed (2015)
26 Geotechnical investigation and foundation recommendation for the proposed buildings at various locations in the Kumbakonam Municipality The Commissioner Kumbakonam Municipality Completed (2015)
27 Geotechnical Investigation and foundation recommendation for the Proposed Construction of subway Southern Railway Tiruchchirappalli Completed (2015)
28 Soil suitability study for embankment formation of NH67 Madhucon Projects Ltd. Completed (2015)
29 Geotechnical investigation and foundation recommendation-BHEL project BHEL Trichy Completed (2015)
30 Soil analysis for railway embankment formation suitability study Southern Railway Tiruchchirappalli Completed (2015)
31 Geotechnical investigation and foundation recommendation-Duraisamipuram, Vannarapettai , Sambathottam and Ariyalur Tamilnadu Slum Clearance Board, Trichy Completed (2015 & 2016)
32 Geotechnical Investigation and pile analysis for proposed erection of seamless communication tower by Fishing Harbour division Fishing Harbour project division, Chennai Completed (2016)
33 Subgrade soil suitability and soil stabilization study for Air Force Station Sulur Garrison Engineer, Military Engineering Service Completed (2016)
34 Geotechnical investigation and foundation recommendation- Narimedu in Pudukkottai Town Tamilnadu Slum Clearance Board, Trichy Completed (2017)
35 Geotechnical consultancy for Trichy Airport expansion work AAI-Trichy Completed (2018)
36 Geotechnical investigation and foundation recommendation for Tamilnadu Slum Clearance Board projects at Melur and Theni Tamilnadu Slum Clearance Board, Trichy Completed (2018)
37 Geotechnical consultancy for Madurai Airport expansion work AAI-Madurai Completed (2018)
38 Investigation of Cochin Airport Runway, Taxiway, Apron pavement stripping due to flood using GPR Cochin Airport Completed (2019)
39 Pile capacity analysis for the proposed Honnavar Port in Karnataka L & T Infrastructure Engineering Ltd. Completed (2019)
40 Proof checking of minor bridges and retaining wall design of the proposed Samayapuram Service Road, NH45. Trichy Padalur Tollways Pvt.Ltd. Completed (2019)
41 Geotechnical consultancy Services for Coimbatore Airport expansion work AAI-Coimbatore Completed (2019)
42 Geotechnical consultant for the proposed LOKICHAR-LAMU crude oil pipeline Project at Kenya(International consultancy Project) SGS Kenya Completed (2020)
43 Geotechnical consultancy Services for Madurai Airport expansion work AAI-Madurai Ongoing